In short: In ERCOT, transmission costs are allocated to large loads using four coincident peak, or 4CP. A facility's metered demand during the single 15-minute interval of highest total ERCOT demand in each of June, July, August and September is averaged, and that average sets its transmission charge for the whole of the following calendar year. The intervals are not announced in advance and are only confirmed afterwards, so managing the exposure is a forecasting exercise, not a scheduling one.
A Year of Cost, Decided in an Hour of Summer
Most discussion of power cost for a data center or a mining site stops at the energy rate. That is the number in the quote, the number in the spreadsheet, and the number that gets compared between sites. In ERCOT it is not the number that decides the bill.
Transmission cost in ERCOT is not billed as a rate on every kilowatt-hour you consume. It is billed as a charge derived from your demand at four specific moments in the previous year. Consume heavily at those four moments and you carry an elevated transmission charge for twelve months regardless of how your consumption behaves in the intervening time. Hold your demand down through them and the same facility, consuming the same annual energy, pays materially less.
The mechanism rewards something unusual: not efficiency, not load factor, and not total consumption, but the ability to be small at precisely the right moments.
What 4CP Actually Measures
ERCOT settles the wholesale market in 15-minute intervals. Across each of the four summer months, one of those intervals is the one in which total demand across the ERCOT region reaches its highest point for that month. Those four intervals are the coincident peaks.
A load's own metered demand during each of those four intervals is recorded. The four figures are averaged. That average becomes the billing determinant used to allocate transmission costs to that load for the following calendar year.
Two features of that definition drive everything that follows. The first is that it is coincident: what matters is your demand at the moment the system peaks, not the moment you peak. A facility that runs its own highest load in February is unaffected by that fact. The second is that the measurement is retrospective. The intervals are identified from settlement data after the month closes. Nobody can tell you on the day that the interval now in progress is the one that will count.
Why ERCOT Works This Way
ERCOT is unusual among US power markets in that it operates as an electrically islanded, intrastate grid, which places most of its transmission service outside the jurisdiction that governs interstate transmission under the Federal Power Act. Where other regions take transmission service under a federally approved open access tariff, ERCOT's transmission cost recovery is structured under state oversight, and the 4CP method is part of that structure.
The logic behind peak-based allocation is defensible on its own terms. Transmission infrastructure is built to carry the maximum flow the system has to serve, not the average. A load that contributes to the system maximum is a load that contributes to the need for that infrastructure, so allocating the cost in proportion to contribution at the peak is an attempt to charge for what the network was actually sized for. Whether four intervals is a statistically robust proxy for that contribution is a separate argument, but the intent is not arbitrary.
Who Is Exposed and Who Is Not
This does not apply to every customer. Allocation on a 4CP basis reaches large loads taking service at transmission voltage, and large loads at distribution voltage whose tariff passes the allocation through. The threshold, the exact mechanism and the pass-through treatment vary by transmission and distribution utility.
That makes it a question to settle before a site is committed. The answer depends on the service voltage you will take, which utility territory the site sits in, and which tariff schedule you qualify for. Those are the same variables that drive the transmission versus primary service voltage decision, and 4CP exposure belongs in that analysis rather than being discovered after energization. The broader structure of large-load utility tariffs is where the rest of the non-energy charges live.
The Forecasting Problem
Because the peak is only knowable afterwards, avoiding it means acting on probability. In practice the distribution is not uniform: the ERCOT system peak in each summer month overwhelmingly lands on a hot weekday afternoon, in a fairly narrow band of late-afternoon hours, when air-conditioning load across the region is highest and solar output has begun to fall off while demand has not.
Operators and forecasting services use weather forecasts and load models to estimate, day by day, the probability that a given afternoon will contain the monthly peak. A load managing its 4CP exposure curtails on high-probability days.
The cost of that strategy is the part that is easy to underestimate. Because you are acting on probability rather than certainty, you will curtail on days that turn out not to matter. A disciplined 4CP program in a given summer involves curtailing across considerably more intervals than the four that eventually count. The right way to evaluate it is as a portfolio: total revenue forgone across every curtailed interval, set against the transmission charge avoided for the following year.
What It Costs You to Be Small
For a facility whose output is continuous and whose revenue is roughly linear in uptime, curtailment is straightforwardly forgone revenue. A mining site gives up hashrate. An AI training cluster gives up compute hours, and depending on how jobs are checkpointed, may give up more than the curtailed hours alone if work has to be repeated.
This is where the two sides of the calculation are genuinely different by workload. Flexible, interruptible, batch-shaped load can step down for an afternoon at a cost that is close to the direct value of the lost hours. Latency-sensitive or contractually committed load cannot, or can only do so by drawing on on-site generation or storage, which converts the question into a different one about fuel cost and equipment wear. A facility built with curtailment in mind treats this as a designed capability rather than an emergency measure.
Where This Sits Alongside Demand Response
4CP avoidance is frequently confused with demand response, and they are not the same thing. Demand response and ancillary services are programs that pay a load for being available to reduce consumption, settled under their own rules. 4CP avoidance pays nothing. It reduces a cost that would otherwise appear in next year's transmission charges.
The two can be pursued together, and large flexible loads often do. But the hours do not always align, the obligations can conflict, and the economics have to be modeled jointly rather than added together. A program that commits you to be available during a window is not automatically compatible with a strategy of being absent during a different window.
The Comparison This Breaks
The most practical consequence of 4CP is what it does to site comparison. A cent-per-kilowatt-hour figure from a Texas site and a cent-per-kilowatt-hour figure from a site in another market are not comparable quantities, because they do not contain the same things. Transmission cost allocation differs by region, and the method, the measurement window and the number of peaks used all differ.
The comparison only becomes meaningful once the full delivered cost has been assembled on each market's own terms: energy, transmission, distribution, ancillary services and any capacity construct the market operates. That is the same discipline that applies to power procurement generally and to site selection, where the headline rate is reliably the least informative number on the page.
For a load with genuine flexibility, ERCOT's structure is an opportunity rather than a penalty: it is one of the few places where the ability to stop for an afternoon converts directly into a lower fixed cost for the following year. For a load without that flexibility, it is a cost that has to be forecast and budgeted, and the worst outcome is the one where it was neither.
Frequently Asked Questions
What does 4CP stand for in ERCOT?
4CP stands for four coincident peak. It is the method ERCOT uses to allocate transmission costs to large loads. The relevant measurement is a load's own demand during the single 15-minute settlement interval in which total ERCOT system demand reaches its highest point in each of June, July, August and September. Those four readings are averaged, and that average sets the load's transmission charge for the following calendar year.
Who actually pays a 4CP-based transmission charge?
Allocation on a 4CP basis applies to large loads taking service at transmission voltage and to certain large loads served at distribution voltage under tariffs that pass the allocation through. A small commercial or residential customer is not billed this way. Whether a specific facility is exposed to 4CP depends on its service voltage, its transmission or distribution service provider, and the tariff it takes service under, so it is a question to settle with the utility before a site is committed rather than after.
Can a data center know in advance when a 4CP interval will occur?
No. The peak is only identifiable after the fact, once ERCOT publishes settlement data for the month. Operators manage the exposure by forecasting: hot weekday afternoons in late summer, typically in the late afternoon hours, carry by far the highest probability, and several forecasting services publish day-ahead probability estimates that large loads use to decide whether to curtail. The practical consequence is that avoiding 4CP means curtailing on more days than the four that ultimately count.
Does curtailing for 4CP conflict with demand response revenue?
They can overlap but they are separate programs with separate economics. Demand response and ancillary service programs pay a load to be available to reduce consumption, and settle on their own schedules and terms. 4CP avoidance is not a payment at all; it is an avoided cost that appears as a lower transmission charge in next year's bills. A load can pursue both, but the hours do not always coincide and the two need to be modeled together rather than assumed additive.
Do other US power markets allocate transmission cost the same way?
No, and this is one of the clearest reasons a power price quoted in one market does not transfer to another. Transmission cost allocation differs by region, and other organized markets use their own peak-based or demand-based methods with different measurement windows and different numbers of peaks. A comparison between a Texas site and a site in another market is not complete until the transmission component has been compared on each market's own terms.
Power Strategy, Not Just a Power Price
Rax Data & Energy sites and operates capacity in US markets where the tariff structure, not only the energy rate, decides the delivered cost. Tell us about your load and we will walk through how it would actually be billed.