Curtailment Updates
Official utility curtailment notices for Rax hosting sites. Review scheduled and mandatory power curtailments affecting operations.
Recent Curtailment Notices
Utility curtailments are a standard part of operating grid-connected hosting infrastructure. When the regional power grid operator or local utility requests a temporary reduction in load, hosted operations pause and resume once the curtailment is lifted. Below are the most recent notices, listed newest first.
Important Notification: Potential Utility Curtailments Due to Extreme Heat (Nebraska Site) 9-3-2026
We would like to inform you that the Nebraska Site is expected to experience extremely high temperatures over the next five days.
Due to the increased power demand associated with these conditions, we have been advised to expect mandatory curtailments from the utility provider during peak demand periods.
As these curtailments are utility-directed, they are outside of Rax operational control. Our team will closely monitor the situation and restore mining operations as soon as the utility permits following each curtailment period.
Please expect intermittent downtime over the next five days. We will continue to keep you updated on any significant developments.
Thank you for your understanding and cooperation.
Mandatory Utility Curtailment — August 31, 2026
We would like to inform you of a mandatory utility curtailment scheduled at our Nebraska site on August 31, 2026, from 01:45 PM to 06:30 PM CST. During this period, all miners will be temporarily taken offline.
We appreciate your understanding and cooperation. If you have any questions or concerns, feel free to reach out via our contact page.
Mandatory Utility Curtailment on 8/10/2026
I hope this message finds you well.
We would like to inform you of a mandatory utility curtailment scheduled at our Nebraska site on August 10, 2026, from 01:00 PM to 05:30 PM CST. During this period, all machines will be temporarily taken offline.
We appreciate your understanding and cooperation. If you have any questions or concerns, feel free to reach out.
Mandatory Utility Curtailment on 7/30/2026
We would like to inform you of a mandatory utility curtailment scheduled at our Nebraska site on July 30, 2026, from 03:00 PM to 06:30 PM CST. During this period, all machines will be temporarily taken offline.
We appreciate your understanding and cooperation. If you have any questions or concerns, feel free to reach out.
Service Notice: Mandatory Utility Curtailment — Nebraska Site (July 28, 2026)
We want to inform our customers of a mandatory utility curtailment scheduled at our Nebraska site on July 28, 2026, from 11:50 PM to 6:30 AM CST. During this period, all machines will be temporarily taken offline.
Temperatures are expected to be exceptionally high today, so there is a possibility that the curtailment may be extended. If that happens, we will keep you informed and provide updates as soon as we receive them.
We appreciate your understanding and cooperation. If you have any questions or concerns, please feel free to reach out to our team.
Mandatory Utility Curtailment — Nebraska Site — July 25, 2026
Mandatory Utility Curtailment Notice
We would like to inform all hosted mining clients of a mandatory utility curtailment scheduled at our Nebraska hosting site on July 25, 2026, from 12:00 PM to 01:00 PM CST. During this period, all hosted machines at the site will be temporarily taken offline in compliance with the utility's curtailment request.
Mining will resume automatically once the curtailment period ends. No action is required on your part.
If the curtailment is extended beyond 01:00 PM CST, we will notify you promptly through email and this page will be updated.
What Is a Utility Curtailment?
A utility curtailment is a request from the regional power grid operator or local utility for large electricity consumers to temporarily reduce their load during periods of peak demand. These events are part of demand-response programs that help maintain grid stability, particularly during extreme weather or when generation capacity is tight.
Curtailment participation is a standard part of operating large-scale computing and mining facilities. Many hosting agreements include curtailment provisions because they benefit both the grid and the operation.
How This Benefits Our Clients
Participating in demand-response and curtailment programs provides tangible advantages for hosted mining operations:
- Reduced electricity rates. Utilities offer lower base rates to customers who agree to participate in curtailment events, directly lowering operating costs for your miners.
- Grid reliability. By cooperating with curtailment requests, we maintain a strong relationship with our utility provider, ensuring continued access to competitive power rates and reliable service.
- Regulatory compliance. Voluntary participation in demand-response programs demonstrates responsible energy use, which supports favorable regulatory treatment for the mining industry as a whole.
What to Expect
- Downtime window: July 25, 2026, 12:00 PM to 01:00 PM CST (approximately 1 hour).
- Affected equipment: All hosted machines at the Nebraska site.
- Automatic restart: Machines will power back on and resume mining automatically when the curtailment period ends.
- Hashrate impact: You may see a temporary dip in reported hashrate during the curtailment window on your pool dashboard. This is expected and will recover fully after restart.
Questions or Concerns?
If you have any questions about this curtailment event or your hosting agreement, please do not hesitate to reach out to our team. We appreciate your understanding and cooperation, and we will keep you informed of any changes to the schedule.
We appreciate your continued trust in Rax as your hosting partner.
Scheduled Utility Curtailment — Nebraska Site — July 20, 2026
Scheduled Utility Curtailment Notice
We are notifying all hosted mining clients of a mandatory utility curtailment at our Nebraska hosting site on July 20, 2026, from 8:30 AM to 12:00 PM CST. During this window, all hosted machines at the site will be temporarily powered down in compliance with the utility's curtailment request.
Mining will resume automatically once the curtailment period ends. No action is required on your part.
If the curtailment is extended beyond 12:00 PM CST, we will notify you promptly through email and this page will be updated.
What Is a Utility Curtailment?
A utility curtailment is a request from the regional power grid operator or local utility for large electricity consumers to temporarily reduce their load during periods of peak demand. These events are part of demand-response programs that help maintain grid stability, particularly during extreme weather or when generation capacity is tight.
Curtailment participation is a standard part of operating large-scale computing and mining facilities. Many hosting agreements include curtailment provisions because they benefit both the grid and the operation.
How This Benefits Our Clients
Participating in demand-response and curtailment programs provides tangible advantages for hosted mining operations:
- Reduced electricity rates. Utilities offer lower base rates to customers who agree to participate in curtailment events, directly lowering operating costs for your miners.
- Grid reliability. By cooperating with curtailment requests, we maintain a strong relationship with our utility provider, ensuring continued access to competitive power rates and reliable service.
- Regulatory compliance. Voluntary participation in demand-response programs demonstrates responsible energy use, which supports favorable regulatory treatment for the mining industry as a whole.
What to Expect
- Downtime window: July 20, 2026, 8:30 AM to 12:00 PM CST (approximately 3.5 hours).
- Affected equipment: All hosted machines at the Nebraska site.
- Automatic restart: Machines will power back on and resume mining automatically when the curtailment period ends.
- Hashrate impact: You may see a temporary dip in reported hashrate during the curtailment window on your pool dashboard. This is expected and will recover fully after restart.
Questions or Concerns?
If you have any questions about this curtailment event or your hosting agreement, please do not hesitate to reach out to our team. We are here to help and will keep you informed of any changes to the schedule.
We appreciate your understanding and continued trust in Rax as your hosting partner.
Mandatory Utility Curtailment — Nebraska Site (July 8, 2026)
This notice is to inform our clients and partners of a mandatory utility curtailment scheduled at our Nebraska hosting site on July 8, 2026.
The curtailment is set to begin at 1:25 PM (site local time). During this window, all machines at the Nebraska site will be temporarily taken offline.
We will provide a follow-up update with the expected end time as soon as it becomes available.
What Is a Utility Curtailment?
Utility curtailments are a standard part of operating grid-connected mining infrastructure. When the local utility requests a temporary reduction in load -- typically to help maintain grid stability during periods of high demand -- hosted operations pause and then resume once the curtailment is lifted. We prioritize keeping our clients informed throughout, and we will post an update here as soon as the site is back online.
Thank you for your understanding.
Mandatory Utility Curtailment (Nebraska Site) 6-30-2026
We would like to inform you of a mandatory utility curtailment scheduled at our Nebraska site on June 30 2026 from 01:15 PM to 07:30 PM CST. During this period, all machines will be temporarily taken offline.
We appreciate your understanding and cooperation. If you have any questions or concerns, feel free to reach out.
Important: Mandatory Utility Curtailment (Nebraska Site) 6-29-2026
We would like to inform you of a mandatory utility curtailment scheduled at our Nebraska site on June 29 2026 from 01:00 PM to 08:30 PM CST. During this period, all machines will be temporarily taken offline.
We appreciate your understanding and cooperation. If you have any questions or concerns, feel free to reach out.
Mandatory Utility Curtailment (Nebraska Site) 6-17-26
We would like to inform you of a mandatory utility curtailment scheduled at our Nebraska site on June 17 2026 from 03:30 PM to 08:30 PM CST. During this period, all machines will be temporarily taken offline.
We appreciate your understanding and cooperation. If you have any questions or concerns, feel free to reach out.
Important: Mandatory Utility Curtailment (Nebraska Site) 6-10-26
Due to extreme heat and weather conditions, there may be unannounced mandatory utility curtailments at our Nebraska site. During these periods, machines may be temporarily taken offline by the utility provider.
Note You are only billed for electricity used.
Mandatory Utility Curtailment (Nebraska Site) 6-9-26
We would like to inform you of a mandatory utility curtailment scheduled at our Nebraska site on June 09 2026 from 03:00 PM to 09:00 PM CST. During this period, all machines will be temporarily taken offline.
We appreciate your understanding and cooperation. If you have any questions or concerns, feel free to reach out.
Mandatory Utility Curtailment (Nebraska Site) 6-5-26
We would like to inform you of a mandatory utility curtailment scheduled at our Nebraska site is scheduled to begin on June 5, 2026, at 08:00 PM CST. During this period, all miners will be temporarily taken offline.
We appreciate your understanding and cooperation.
Mandatory Utility Curtailment (Nebraska Site) 5-15-26
We would like to inform you of a mandatory utility curtailment scheduled at our Nebraska site on May 15 2026 from 03:45 PM to 06:45 PM CST. During this period, all machines will be temporarily taken offline.